Tuesday, June 7: Hallway carpet in, Halfmann & Anderson prep for painting

The hallway is now carpeted, completing the new carpet installation except for installing the hallway's black vinyl wall base and the edging transition between the hallway's carpet and the large room's tile floor.

Ken Halfmann and Mike Anderson started the preparation work of applying a considerable amount of masking tape around the entire large meeting/class/studio room, the last room to be painted. Jim Thornbery helped out some removing wall plates and vacuuming the wall base.

Painting is scheduled to start Thursday during the day. Ken very much needs additional painters, so if you can help please email Camera@PhotoMidwest.Org with the subject line "I want to paint".

What does the new Main Gallery look like? The new lighting is not yet installed in this photograph below of the eastern half of the gallery. The exhibition space continues down the wide hallway to the left.

PhotoMidwest Main Gallery, 700 Rayovac Dr., by Eloisa Calender. All rights reserved.

PhotoMidwest Main Gallery, 700 Rayovac Dr., by Eloisa Calender. All rights reserved.